Elkhorn Ridge – Building relationships with landowners
Buffalo Bear – Layers of rock and elevation changes
Jeffers – 20 foundations in 22 days
Odin – Moving tons of equipment over soft soils
Spanish Fork – Protecting the environment
Skyway Industrial Park – New development in Pipestone
Rock Valley – 6 blocks of concrete overlay in 2 1/2 weeks
Pipestone, Minnesota
Skyway Industrial Park was a new Industrial Development in the City of Pipestone. The city recognized the need for additional space to attract new businesses. Working with the city early on in the process, CCI recommended using a Concrete Alternate. This was first time the city had ever done a concrete paving project with the dowel bar transverse joints.
CCI constructed the Park’s underground infrastructure, as well as the 3/4 mile concrete pavement and 30” curb and gutter. One of the
biggest challenges for this project was the location of the city’s concrete supplier. Their plant was located on a road that was included in the paving project. To overcome this challenge, CCI worked with the concrete supplier to schedule construction activities so the concrete was always accessible out of the plant to the site. The project went smoothly and was successful. The city was very pleased with the outcome.
Project was completed in June 2004.