Wymore Water Project in Beatrice,NE
Carstensen Contracting, Inc., was under a tight schedule to complete all pipe installation prior to Spring planting season to help the owner avoid crop damage expenses. CCI went to work on obtaining Results. The installation of 157 miles of pipe and 215 bores was completed in April, just a short 3 1/2 months after beginning work in December.